91= Muscat & Salalah International Airport Expansion
Project Overview
The project to increase the capacity of Oman’s
main airport to 7 million passengers a year comprises five phases. The first includes upgrading the existing runway, building a new 4.3km-long runway, and improving taxiways, access roads and other airside facilities.
Project analysis
Muscat prioritises transport schemes
While Oman is making headway with plans to develop its airports, ports and freezones, the country’s first railway project has fallen behind due to the current political situation
Company profiles
Ominvest
The investment firm’s decision to diversify into tourism marks a change in strategy
Oman Air
Muscat’s flag carrier is pushing ahead with aggressive international expansion plans, despite losses
Galfar Engineering & Contracting
Oman’s largest contractor must look further afield to win contracts and find growth
Key Facts
Client: Transport & Communication Ministry
Sector: Transport
Stage: Execution
Budget: $4.7bn
Completion date: Q1 2013
Location: Oman
News
Oman awards final package at Muscat and Salalah airports
Oman contract covers passenger boarding bridges
-
Oman delays award of three airport contracts
-
Oman receives bids for Sohar airport
-
Oman delays package three award for four airports
-
Oman to award final packages for Muscat and Salalah airports
-
Oman awards two contracts at Muscat and Salalah airports
-
US surveillance firm Era wins contract at Oman airports
-
Oman receives three bids for Duqm airport
MEED Projects