Office National de l’Electricite sets March date for proposals
Morocco’s Office National de l’Electricite has delayed the bid deadline for the planned Safi independent power project (IPP) to 12 March.
Developers had been due to submit their proposals for the 1,320MW coal-fired plant on 31 October.
In mid May, the client decided to move the proposed plant to a location 7 kilometres away from the original site, following significant changes to the scope of the project (MEED 22:5:09).
Under its original plan, the utility had assumed responsibility for the supply of coal feedstock and the construction of coal-handling facilities at Safi port. In March, the utility shifted this responsibility onto the developer.
You might also like...
Saudi Arabia seeks K9 PPP project interest
25 April 2024
Kuwait reviews 1.1GW solar prequalifications
25 April 2024
LIVE WEBINAR: Abu Dhabi Oil & Gas 2024
25 April 2024
Qiddiya tenders site office package
25 April 2024
A MEED Subscription...
Subscribe or upgrade your current MEED.com package to support your strategic planning with the MENA region’s best source of business information. Proceed to our online shop below to find out more about the features in each package.