Saudi Aramco invites developers for power and steam projects

01 March 2012

Developers to respond to request for qualification by 11 March for Aramco’s Eastern Province schemes

Saudi Aramco has issued a request for qualification (RFQ) to developers to build three greenfield gas-fired electricity and steam plants in Saudi Arabia’s Eastern Province.

The projects will be located at Abqaiq, Hawiyah and Ras Tanura, and will have a total installed capacity of about 770MW of power and 2.95 million pounds an hour in steam output.

While the exact scope of the projects is being determined by Saudi Aramco, the facilities are likely to have the following capacities:

  • Abqaiq – 320MW and 1,200 thousand pounds an hour
  • Hawiyah – 130MW and 550 thousand pounds an hour
  • Ras Tanura – 320MW and thousand pounds an hour

The schemes will be built as independent power projects (IPPs) on a build, own, operate and transfer basis, with the ownership of each project being transferred to Aramco 20 years after the start of commercial operations.

Each of the projects will convert fuel gas and feed water provided by Aramco into electricity and steam for sale to Aramco under an energy conversion agreement.

Aramco may participate in the equity of the project company and may hold up to 50 per cent of the voting and economic rights, with the remaining voting and economic rights held by the selected developer group.

Each of the consortium members will be required to hold at least 20 per cent of the voting and economic rights held by the applicant in the project company upon its formation.

Developers must submit proposals for all three projects to be eligible. Companies must respond to the RFQ by 11 March.

Aramco will select qualified applicants by 22 April and issue a request for proposals (RFP) on 23 April. Bids are to be submitted by 1 September and Aramco will award a contract for the three projects by 31 December. Financial close is scheduled to occur by 25 March 2013.

The selected developer will be required to construct the projects to meet the following project commercial operation dates:

  • Hawiyah: November 2015
  • Abqaiq: January 2016
  • Ras Tanura: March 2016

A MEED Subscription...

Subscribe or upgrade your current MEED.com package to support your strategic planning with the MENA region’s best source of business information. Proceed to our online shop below to find out more about the features in each package.