The two local contractors were part of a consortium with South Africa's Murray & Roberts Contractors (Middle East) for the project, but Tameer cancelled its contract with the original consortium in March (MEED 30:4:09).
The project is on Reem island and involves building six towers between the sea and the Central Park area of the Shams Abu Dhabi development.
The main buildings are a 74-floor, 300 metre-high office tower in the commercial area, a 21-floor hotel and apartment tower, two 50-floor residential towers and two 30-floor residential towers.
The total built-up area is 915,000 square metres. The first units are scheduled for delivery in 2011.
The US' Hill International is the project manager and France's Bureau Veritas is construction manager.
You might also like...
Chinese firm to build Oman wind turbine factory
09 June 2026
Abu Dhabi selects team for 3.3GW Al-Nouf IPP
09 June 2026
Zoom launches new Saudi data centre at center3
09 June 2026
A MEED Subscription...
Subscribe or upgrade your current MEED.com package to support your strategic planning with the MENA region’s best source of business information. Proceed to our online shop below to find out more about the features in each package.
Take advantage of our introductory offers below for new subscribers and purchase your access today! If you are an existing client, please reach out to your account manager.