Acciona confirms $500m Facility E deal

05 December 2024
The contract Acciona won is part of the Facility E $2.8bn EPC package

Register for MEED's 14-day trial access 

Spanish contracting firm and utility investor Acciona has been awarded a contract to design and build a seawater reverse osmosis (SWRO) plant as part of Qatar’s Facility E independent water and power project (IWPP) in Ras Abu Fontas.

According to the company, the plant will have a capacity of 500 million litres a day, equivalent to supplying 2 million people with drinkable water, and has a budget of around $500m (€475m).

MEED previously reported that the integrated facility’s water desalination package will have a capacity of 110 million imperial gallons a day (MIGD), while the power generation plant will have the capacity to generate 2,415MW of electricity.

The contract Acciona won is part of the $2.8bn overall engineering, procurement and construction (EPC) package of the Facility E IWPP, which South Korea’s Samsung C&T will implement.

Japan's Sumitomo Corporation leads a consortium that will develop and operate the Facility E IWPP. The team includes fellow Japanese utility developer Shikoku Electric, Seoul-headquartered Korea Overseas Infrastructure & Urban Development Corporation (KIND) and Korea Southern Power Company (Kospo).

The total project cost is roughly $3.7bn.

Japan’s Mitsubishi Power will supply the gas turbines for the power plant.

The four developer consortium members, along with Qatar Electricity & Water Company (QEWC) and QatarEnergy (QE), will establish a project company.

According to Sumitomo, the equity distribution between the project company shareholders is:

  • Sumitomo Corporation: 17%
  • Shikoku Electric: 11%
  • Kospo: 6%,
  • KIND: 6%
  • QEWC: 55%
  • QE: 5%

MEED understands that the new target commercial operation date for the Facility E IWPP project has been moved to 2029. 

According to Acciona, Qatar achieved its first milestone in reverse osmosis technology at its Ras Abu Fontas 3 plant, with a capacity of 165,000 cubic metres a day (cm/d).

It is understood that Acciona also built the Umm Al-Houl 1 and 2 desalination plants in Doha, which each have a production capacity of 284,000 cm/d.

The state utility’s transaction advisory team includes UK-headquartered PwC and Clyde & Co as financial and legal advisers, respectively, led by Belgrade-headquartered Energoprojekt as technical adviser.

Facility E is Qatar’s fifth IWPP scheme. Completed and operational IWPPs include three projects in Ras Laffan – known as Facilities A, B and C – and Facility D in Umm Al-Houl.

Awarded in 2015 and completed in 2018, Facility D was developed by a Japanese consortium of Mitsubishi Corporation and Tokyo Electric Power Company (Tepco). South Korea’s Samsung C&T was the EPC contractor.

Related readFacility E award marks key milestone

A MEED Subscription...

Subscribe or upgrade your current MEED.com package to support your strategic planning with the MENA region’s best source of business information. Proceed to our online shop below to find out more about the features in each package.

Take advantage of our introductory offers below for new subscribers and purchase your access today! If you are an existing client, please reach out to your account manager.