Due date for bids pushed back for a third time
The bid deadline for the three main engineering, procurement and construction (EPC) packages of Saudi Aramcos project to expand its Haradh gas facility have been extended for a third time.
Originally contractors were meant to submit bids for the three packages on 3 July. This was then pushed back to 1 August, then 14 August.
The latest deadline to be set is 22 August.
The three packages are:
- Package One - North Haradh Compression Plants (estimated budget: $1bn-$1.2bn)
- Package Two - Satellite Haradh Compression Plants (estimated budget: $1bn-$1.2bn)
- Package Three - South Haradh Compression Plants (estimated budget: $1bn-$1.2bn)
All three of the packages are part of a larger megaproject to expand gas processing capacity at Haradh and Hawiyah, which is expected to be worth $4.5bn.
Saudi Aramcos Hawiyah Gas Plant Expansion project is also a package in the larger $4.5bn megaproject. It is extimated to have a value of between $1bn-$1.3bn.
The Hawiyah Gas Plant Expansion project saw bids submitted on 13 August. The bid deadline was extended twice before bids were submitted.
The $4.5bn megaproject will expand existing facilities giving them the capacity to process more than 1 billion cubic feet a day (cf/d) of additional gas produced at the Ghawar onshore oil field the largest in the world.
You might also like...
UAE bank asset quality hinges on property market
03 April 2026
Safety and security matters
03 April 2026
Saudi forecast remains one of growth
03 April 2026
A MEED Subscription...
Subscribe or upgrade your current MEED.com package to support your strategic planning with the MENA region’s best source of business information. Proceed to our online shop below to find out more about the features in each package.
Take advantage of our introductory offers below for new subscribers and purchase your access today! If you are an existing client, please reach out to your account manager.