King Salman International Airport Development Company (KSIADC), backed by Saudi Arabia’s Public Investment Fund, has received prequalification forms from firms for a contract to develop the third runway and taxiways at King Salman International airport (KSIA) in Riyadh.
MEED understands that firms submitted the statements on 18 January.
KSIADC received interest from firms on 18 December for the package.
It is understood that the third runway will add to the two existing runways at Riyadh’s King Khalid International airport, which will eventually become part of KSIA.
KSIADC prequalified firms in September for the main engineering, procurement and construction (EPC) packages, early and enabling works, specialist systems and integration, specialist systems, materials and equipment, engineering and design, professional services, health, safety, security, environment and wellbeing, modular installation and prefabrication, local content and environmental, social and governance (ESG), and other services.
The entire scheme is divided into eight assets. These include:
- Iconic Terminal
- Terminal 6
- Private aviation terminal
- Central runway and temporary apron
- Hangars
- Landside transport
- Cargo buildings
- Real estate
In August, KSIADC confirmed signing up several architectural and design firms for the various elements of the project.
KSIADC confirmed that it signed up UK-based Foster + Partners to design the airport’s masterplan, including the terminals, six runways and a multi-asset real estate area.
US-based engineering firm Jacobs will provide specialist consultancy services for the masterplan and the design of the new runways.
The client also confirmed the appointment of UK-based engineering firm Mace for the delivery partner role on the project.
The airspace design consultancy contract was awarded to the local firm Nera.
Project scale
The project covers an area of about 57 square kilometres (sq km), allowing for six parallel runways, and will include the existing terminals at King Khalid International airport. It will also include 12 sq km of airport support facilities, residential and recreational facilities, retail outlets and other logistics real estate.
If the project is completed on time in 2030, it will become the world’s largest operating airport in terms of passenger capacity, according to GlobalData.
The airport aims to accommodate up to 120 million passengers by 2030 and 185 million by 2050. The goal for cargo is to process 3.5 million tonnes a year by 2050.
Saudi Arabia plans to invest $100bn in its aviation sector. Riyadh’s Saudi Aviation Strategy, announced by the General Authority of Civil Aviation (Gaca), envisages tripling Saudi Arabia’s annual passenger traffic to 330 million travellers by 2030.
It also aims to increase air cargo traffic to 4.5 million tonnes and raise the country’s total air connections to more than 250 destinations.
READ THE FEBRUARY MEED BUSINESS REVIEW
Trump unleashes tech opportunities; Doha achieves diplomatic prowess and economic resilience; GCC water developers eye uptick in award activity in 2025.
Published on 1 February 2025 and distributed to senior decision-makers in the region and around the world, the February MEED Business Review includes:
> AGENDA 1: Trump 2.0 targets technology > AGENDA 2: Trump’s new trial in the Middle East > AGENDA 3: Unlocking AI’s carbon conundrum > GAZA: Gaza ceasefire goes into effect > LEBANON: New Lebanese PM raises political hopes > WATER DEVELOPERS: Acwa Power improves lead as IWP contract awards slow > WATER & WASTEWATER: Water projects require innovation > INTERVIEW: Omran’s tourism strategies help deliver Oman 2040 > PROJECTS RECORD: 2024 breaks all project records > REAL ESTATE: Ras Al-Khaimah’s robust real estate boom continues > QATAR: Doha works to reclaim spotlight > GULF PROJECTS INDEX: Gulf projects market enters 2025 in state of growth > CONTRACT AWARDS: Monthly haul cements record-breaking total for 2024 > ECONOMIC DATA: Data drives regional projects > OPINION: Between the extremes as spring approaches |
You might also like...
Local contractor wins Madinah substation contract
26 March 2026
Neom terminates $5bn Trojena dams contract with WeBuild
26 March 2026
Egypt discovers more gas in its Western Desert region
26 March 2026
Iraq gas field project disrupted by regional conflict
26 March 2026
A MEED Subscription...
Subscribe or upgrade your current MEED.com package to support your strategic planning with the MENA region’s best source of business information. Proceed to our online shop below to find out more about the features in each package.
Take advantage of our introductory offers below for new subscribers and purchase your access today! If you are an existing client, please reach out to your account manager.