Local company Alsa Engineering submitted lowest bid
The UAE-based Alsa Engineering is the frontrunner for the engineering, procurement and construction (EPC) contract on the acid gas flare system at the Habshan gas processing and distribution hub in Abu Dhabi.
Abu Dhabi Gas Industries (Gasco) received a $35m bid from Alsa, which is about 10 per cent lower that the $39m price submitted by Pakistan’s Descon.
The other bidders are Athens-based Consolidated Contractors Company (CCC), the UAE-based Dodsal, India’s Punj Lloyd, and France’s Technip.
Australia’s WorleyParsons is conducting the front-end engineering and design work for the project. Tebodin of the Netherlands has been tasked with the project management consultancy (MEED 8:4:11).
You might also like...
TotalEnergies to acquire remaining 50% SapuraOMV stake
26 April 2024
Hyundai E&C breaks ground on Jafurah gas project
26 April 2024
Abu Dhabi signs air taxi deals
26 April 2024
Spanish developer to invest in Saudi housing
26 April 2024
A MEED Subscription...
Subscribe or upgrade your current MEED.com package to support your strategic planning with the MENA region’s best source of business information. Proceed to our online shop below to find out more about the features in each package.