Middle East contracts awarded: November 2007

02 December 2007

Almost $2.4bn worth of contracts were awarded across the Middle East region in November, according to this selected checklist compiled from MEED reports throughout the month.

For more up to date information on the region’s largest projects, go to www.meedprojects.com, which tracks $1.7trillion worth of projects.

Table: Contracts awarded in November 2007

ProjectContractorClientEstimated value ($m)Date
Algeria
Marine survey on planned Galsi gas pipeline to Italy; includes survey of landing points in Algeria, Sardinia and ItalyFugro (Netherlands)Galsi S.p.A2602/11/2007
Build gas compression facilities at Salah fieldPetrofac InternationalConsortium of the BP (UK), Statoil (Norway) and state energy company Sonatrach60030/11/2007
Egypt
Front-end engineering and design contract; covers onshore processing facilities for 300 million cubic feet a day of gas and 4,000 barrels a day of condensate on the Abu Sir and El-King fieldsKBR (US)North Alamein Petroleum Company (Nalpetco)1002/11/2007
Kuwait
Build Siddiq W 300/132-kV substation, and expand Ahmadi W 132/11-kV substation to 300 kVSiemens - GermanyElectricity & Water Ministry9326/11/2007
Provide oil field services, including coiled tubing, slicklines and well-lines, wellhead maintenance, surface well testing facilities and logging servicesGulf Drilling & Maintenance CompanyKuwait Oil Company (KOC)24.327/11/2007
Build control and meteorology centres at Kuwait International AirportSyed Hamid Behbehani & Sons CompanyDirectorate General of Civil Aviation3827/11/2007
Build Kuwait’s first reverse osmosis desalination plantDoosan Heavy Industries & Construction (South Korea)Electricity & Water Ministry32030/11/2007
Oman
Build third production line at plant near MuscatChina National Building Material Equipment Corporation (China)Oman Cement Company16209/11/2007
Carry out two-rig drilling programmeDalma Energy & Company (Muscat)BPna09/11/2007
Collect seismic data over 2,800 sq kms at central Khazzan and Makarem tight gas fieldsGlobal Geophysical Services (US)BPna09/11/2007
Process new seismic data and reprocess existing seismic data at central Khazzan and Makarem tight gas fieldsPGS Data Processing (Norway)BPna09/11/2007
Carry out front-end engineering and design contract. Covers evaluation of options for appraisal phase of early production from central Khazzan and Makarem tight gas fieldsWorleyParsons- AustraliaBPna09/11/2007
Qatar
Engineering, procurement and construction contract for gas treatment centres on Qatalum aluminium smelter at Mesaieed industrial areaSolios Environement (France)Qatalumna02/11/2007
Front-end engineering and design contract on plant planned at MasaieedUhdeQatar Petrochemical Company (Qapco)na25/11/2007
Saudi Arabia
Build container terminal at Jeddah Islamic PortChina Harbour Engineering CompanySaudi Trade & Export Development Company (Tusdeer)na09/11/2007
Supply three compression trains for olefins and styrene complex in Jubail - supply cracked gas, propylene refrigerant and binary refrigerant compressorsGE Oil & Gas (Florence)National ChevronPhillipsna15/11/2007
Work on expansion of the Hajj terminal and construct facilities for docking Airbus A380 superjumbosAl Shaer EngineeringSaudi Binladin Group6922/11/2007
UAE
Carry front-end engineering and design on the Asab, Bab, Bu Hasa and Ruwais modifications projectVeco (US/Canada)Abu Dhabi Gas Industries Company (Gasco)na02/11/2007
Install electrical and telecoms systems and street lighting for Jumeirah Golf Estates schemeAl-Buraq ContractingIstithmar Leisure4709/11/2007
Carry out underground piping work for Jumeirah Golf Estates schemeETA Ascon (Dubai)Istithmar Leisure5109/11/2007
Build Agronomy Centre at Jumeirah Golf Estates schemeHennessey ConstructionIstithmar Leisurena09/11/2007
Construction of Gulf hotel development in Abu Dhabi, featuring five-star hotel consisting of several interconnected towers, 105 chalets and a large waterfront with a marina, canals and waterwaysAl-Habtoor Engineering EnterprisesAbu Dhabi National Hotels27209/11/2007
Build eight buildings at Indigo Central development along Sheikh Zayed RoadSystem ConstructIndigo Properties3509/11/2007
Construction of Hasik-Ash Shuwaymiyah Road in Dhofar GovernorateGalfar Engineering and ContractingMinistry of Transport and Communication17712/11/2007
Land levelling contract at Seeb International AirportGalfar Engineering and ContractingMinistry of Transport and Communication4212/11/2007
Expand gas processing facilities at offshore lower and upper Zakum fields; covers installation of two 220 million-cubic-feet-a-day gas injection compressors, air-cooling system, dehydration units, pressure vessels and reboilersConsortium of the National Petroleum Construction Company (NPCC) and Technip (France)Abu Dhabi Marine Operating Company37021/11/2007
Total2,336.3

MEED Projects, tracking $1.7trillion worth of projects, is a subscriber-only service that provides comprehensive, up-to-date and accurate project information. Monitor industry and business development opportunities through market data tailored to your needs.

Be the first to know about new projects; we provide the data so you can win the business.

If you would like to see a demo of MEED Projects, or just want to find out more, register your details on meedprojects.com or call +971 (0) 4 367 1302.

A MEED Subscription...