Companies submit bids to construct first phase of Lower Fars heavy oil development project
UK-based Petrofac has submitted the low bid to Kuwait Oil Company (KOC) for the main contract to build the Lower Fars heavy oil (LFHO) development project.
The firm submitted a KD1.2bn ($4.3bn) engineering, procurement and construction (EPC) bid for the scheme, which is one of the largest upstream projects in the region.
The other bidders were:
- SK Engineering & Construction (South Korea): KD1.3bn
- Saipem (Italy): KD1.7bn
- GS Engineering & Construction (South Korea): KD1.8bn
The single EPC tender is for the first phase of the projects development and includes the construction of a steam injection facility, production facilities, a support complex, tank farms and a 270,000 barrel-a-day (b/d) pipeline to transport the heavy crude to the planned new refinery at Al-Zour in the south of Kuwait.
This initial phase of development will comprise of two well blocks that are expected to reach a plateau production rate of 60,000 b/d over a 10-year period from the start of operations. In total, the blocks will contain more than 1,300 wells. Further phases are expected to ramp up production to a final plateau of 270,000 b/d.
State upstream operator KOC first issued a tender for the phase one facilities in October 2013 and the deadline for bids had been repeatedly delayed. The initial deadline for submissions was 26 January 2014.
The Lower Fars reservoirs contain heavy oil with a gravity ranging from 17 API to as low as 11, compared with Kuwaits regular crude blends, which have an average gravity of about 30 API. It is also highly viscous, in the range of 200 to 1,000 centipoise (CP).
To address this, the project will use the cyclic steam stimulation (CSS) technique, where steam is injected into the reservoir to heat the highly viscous oil, making it easier to pump to the surface.
Based on its reservoir engineering work, KOC has proposed phase one be developed using two or three cycles of CSS, followed by continuous steam flooding. The steam will be produced by several generators at the planned central processing facility (CPF).
Heavy oil from the CPF will be sent without any blending through a new pipeline to the planned New Refinery at Al-Zour, or blended with lighter oil so it can be sent to export markets.
The submission of bids on the scheme comes almost seven years after KOC signed a landmark heads of agreement with US oil major ExxonMobil for the Lower Fars heavy oil development in October 2007. Under the terms of the deal, ExxonMobil was to provide assistance for long-term production of 700,000 b/d of heavy oil under an enhanced technical services agreement.
The deal never progressed, leaving KOC to develop the scheme on its own. It also subsequently revised its heavy oil output targets. The country had originally planned to produce as much as 700,000 b/d of heavy oil. This target has now been significantly scaled back, with KOC planning to ramp up production to 60,000 b/d by 2017, 120,000 b/d by 2020, and as much as 270,000 b/d by 2030.
You might also like...
Adnoc Offshore awards Upper Zakum contract
17 April 2024
Oman awards Batinah coastal road contract
17 April 2024
Oman appoints Al Khuwair Downtown project manager
17 April 2024
A MEED Subscription...
Subscribe or upgrade your current MEED.com package to support your strategic planning with the MENA region’s best source of business information. Proceed to our online shop below to find out more about the features in each package.