Saudi Energy, formerly Saudi Electricity Company, has named four contractors that will deliver electricity infrastructure for the Expo 2030 Riyadh site.
The local Al-Babtain, Haif Company, Alfanar and Trading & Development Partnership (TDP) will construct several substations and connect them to the national grid under an agreement signed between Saudi Energy and Expo 2030 Riyadh Company (ERC).
Saudi Electricity Projects Development Company (PDC), Saudi Energy’s project development arm, will oversee implementation.
The scope includes a main 380/132kV supply station and three primary 132/13.8kV substations as well as associated electricity infrastructure.
In March, MEED reported that Saudi Energy was moving forward with procurement of an engineering, procurement and construction (EPC) contract for three 132/13.8kV substations in Riyadh to support Expo 2030.
The latest agreement is understood to relate to the same substations. According to sources, nine companies submitted bids for the project in June.
These included the following local firms: Al-Babtain Contracting, Al-Gihaz Holding, Al-Haider Company, Alfanar Projects, Haif Company, Mohammed Al-Ojaimi Group, Nesma Infrastructure & Technology and Tareg Al-Jaafari Contracting Establishment.
India’s Larsen & Toubro also submitted a bid for the project.
The infrastructure will provide electricity to the Expo site ahead of the event and allow testing and trial operations to be completed before the Expo opens.
In January, the local firm Nesma & Partners won an estimated SR1bn ($267m) contract to deliver the initial infrastructure works at the Expo site.
Expo 2030 Riyadh is scheduled to take place from 1 October 2030 to 31 March 2031. The event is expected to attract about 42 million visits and will involve 197 participating countries.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF
Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034 > MARKET FOCUS: Maghreb fortunes diverge > INDUSTRY REPORT: GCC banks prove resilient amid turmoil > LEADERSHIP: Private capital and the GCC infrastructure inflection > INTERVIEW: Developers look beyond standalone solar |
You might also like...
KJO allows more time for Dorra gas project PMC bids
17 August 2026
Neom's next phase is crucial to green hydrogen pipeline
17 August 2026
Five bid for King Salman Bay construction work
17 August 2026
PDO allows more time for Al-Ghubar field project prices
17 August 2026
A MEED Subscription...
Subscribe or upgrade your current MEED.com package to support your strategic planning with the MENA region’s best source of business information. Proceed to our online shop below to find out more about the features in each package.
Take advantage of our introductory offers below for new subscribers and purchase your access today! If you are an existing client, please reach out to your account manager.