Tehran grows frustrated over lack of action by Pakistan over multibillion-dollar scheme and is expected to impose harsh fines
Iran is losing patience with Pakistan over its lack of progress on the multi-billion dollar Iran-Pakistan pipeline project.
Iran claims to have already completed 900 kilometres of pipeline on its side of the border and is waiting for Pakistan to fulfil its obligations to construct at least 700km on its side.
However, Iranian media reports say the lack of progress means the deadline for exporting gas, December 2014, has now been missed and it is looking increasingly unlikely that any progress will be made for at least another two years.
Pakistan has sent officials to Tehran to try to negotiate an extension to the agreed terms, but Iran is still expected to impose harsh financial penalties for the delays.
When completed, the pipeline will have the capacity to transport more than 2 billion cubic feet a day (cf/d) of gas to Pakistan.
You might also like...
Energy resilience matters as much as capacity
13 March 2026
Qatar’s new $8bn investment spices up global LNG race
13 March 2026
Risk calculus shifts for regional PPP projects
13 March 2026
A MEED Subscription...
Subscribe or upgrade your current MEED.com package to support your strategic planning with the MENA region’s best source of business information. Proceed to our online shop below to find out more about the features in each package.
Take advantage of our introductory offers below for new subscribers and purchase your access today! If you are an existing client, please reach out to your account manager.