Hamad International airport

14 February 2013

The airport will feature two of the world’s longest runways

Value: $17.5bn

Client

Hamad International airport

Bernardo Gogna, project director

Tel: (+974) 4 467 9777

Consultant

Bechtel

Larry Estrada, project director

Tel: (+974) 4 467 9777

After a series of delays, Qatar’s new international airport is scheduled to fully open in the second half of 2013.

Originally known as New Doha International airport, it was renamed Hamad International airport in January 2013.

The airport will cater to 12 airlines from 1 April, but Qatar’s national carrier, Qatar Airways, will not transfer all its traffic to the new location until the second half of the year.

Hamad International will play a key role in supporting Qatar Airways’ expansion plans. Passenger traffic at the current Doha airport has been increasing by about 14 per cent a year.

Once complete, the airport will feature two of the longest runways in the world, an 85-metre-high control tower and a 510,000-square-metre passenger terminal with 40 gates. The NDIA Steering Committee was set up to manage the project.

Hamad International airport is built on a 22-square-kilometre site, just a few kilometres east of the city’s existing airport. Initial work included the reclamation of 62 million cubic metres of land to create the site.

The project is being developed in three phases. Once work is completed in the second half of 2013, the facility will provide capacity for 28 million passengers a year, a significant increase on the existing airport’s annual capacity of 4.2 million passengers.

US firm Bechtel has been overseeing the project, after winning the engineering, procurement, construction and management contract in 2005. The Sky Oryx joint venture of Turkey’s TAV Construction and Japan’s Taisei was awarded construction contracts for the main terminal building and concourses A, B and C in early 2006.

Hamad International airport has been blighted by a string of delays and contract cancellations since its launch in 2004. In 2008, its schedule was pushed back by two years, bringing its target completion date to 2011.

In 2010, China State Construction Engineering had its building contract for the airport terminated. The deal had covered the construction of 20 buildings, including a general aviation terminal and hangar.

A revised completion date of 12 December 2012 was set, but was missed again, due in part to an ongoing legal battle between Qatar Airways and German/UAE joint-venture construction firm Lindner Depa Interiors (LDI).

LDI is accused of failing to complete the fitout of 19 airport lounges by the summer of 2012, as demanded under its $250m-plus contract. Qatar Airways issued a lawsuit against the company at the end of last year for causing delays to the airport project.

Key dates

January 2004

The US’ Bechtel awarded the engineering, procurement, construction and management contract

January 2005

Groundbreaking ceremony for the airport

March 2006

Sky Oryx awarded construction contracts for the main terminal building and concourses A, B and C

December 2008

Project enters phase 3a: construction of North Node section of the passenger terminal

June 2010

Joint venture of Belgium’s Six Construct and local Midmac Contracting Company awarded $740m contract to build six-level North Node link to the main passenger terminal

October 2010

China State Construction Engineering Corporation’s building contract is terminated

June 2012

German/UAE Lindner Depa Interiors’ October 2011 contract for 19 airport lounges is cancelled

December 2012

Most recently missed completion deadline

April 2013

Partial opening of the new airport

Second Half 2013

Airport intended to be fully operational

Source: MEED

A MEED Subscription...

Subscribe or upgrade your current MEED.com package to support your strategic planning with the MENA region’s best source of business information. Proceed to our online shop below to find out more about the features in each package.