MEW pushes forward with major IWPPs

06 December 2015

Work has finally begun at the Al-Zour North IWPP

As Kuwait faces the realities of ageing power-generation infrastructure and rising demand, the renewed momentum in its private power market could not come at a better time.

The restructured public-private partnership (PPP) sector, led by the Kuwait Authority for Partnership Projects (KAPP), has prioritised independent water and power projects (IWPPs) and learned many lessons from the country’s first attempt to deliver the 1,500MW Al-Zour North project using this structure.

These lessons have been incorporated into the PPP Law of 2014, in a bid to ensure future projects are more attractive to investors and can progress more quickly.

With the country continuing to suffer from power blackouts, the pressure on MEW has mounted

This is extremely welcome for Kuwait’s Ministry of Electricity & Water (MEW), which is responsible for building and maintaining power-generation capacity and delivering water services. It can now push on with several major and much-needed IWPPs in partnership with KAPP.

Slow progress

Schemes such as the 1,500MW Al-Zour North 2 and the 1,800MW Al-Khiran 1 have lingered in the planning stages for many years as the government struggled to get political support for the private model. But with the country continuing to suffer from power blackouts and transmission issues, the pressure on MEW has mounted.

So severe and high profile was a power cut in February 2015 that Minister of Electricity & Water Abdulaziz Abdullatif al-Ibrahim resigned the following month. He was succeeded by Ahmed Khaled Ahmad al-Jasser, but just six months later, at the end of September, the new minister also resigned, following an investigation into the award of emergency power-generation contracts in 2007.

Along with 14 other officials, Al-Jasser sat on an MEW committee to procure 500MW of emergency power generation through a general invitation for proposals, without oversight from the Central Tenders Committee, the State Audit Bureau or the National Assembly. However, some of the second-hand gas turbines imported as part of the contract were unusable, wasting public funds.

Al-Jasser was handed a jail sentence in September for his part in the scandal. He is understood to be appealing against the conviction, but for now his portfolio for power and water has been passed on to the Minister of Cabinet Affairs.

Key Ministry of Electricity & Water projects
ProjectBudget ($m)StatusAward yearDue
Nuwaiseeb independent power project2,500Study20182021
Doha desalination plant: phase 1503Execution20152017
Subiya open-cycle gas turbine: phase 2500Execution20152017
Subiya open-cycle gas turbine: phase 3500Main contract bid20162018
Doha desalination plant: phase 2432Main contract PQ20162020
Al-Zour South conversion to combined cycle: phase 3300Main contract bid20162019
Subiya conversion to combined cycle: phase 2300Main contract bid20162018
Al-Mutlaa high area water storage tanks: phase 2200Main contract bid20152017
Al-Zour North pumping stations200Execution20112016
Sabah al-Ahmed 400kV ground cables: phase 2200Execution20122015
PQ=Prequalification. Source: MEED Projects

Subiya expansion

The need for emergency generation in 2007 was symptomatic of years of under-investment in new generation and transmission capacity. Finally, after many years of planning, the 2,000MW Subiya power plant came online in mid-2012, and today MEW is seeking to expand production at the plant. In September, MEW extended the submission deadline for firms bidding to provide an additional 500MW of generating capacity at the site.

At the same time, construction has begun at the long-awaited Al-Zour North project, after more than five years in the planning stages. When complete, this will bring 1,500MW of new power into the sector along with 107MIGD of desalinated water.

Peak demand

These developments are crucial for Kuwait and the MEW, which forecasts that peak power demand will climb from 12,800MW in 2013 to 22,500MW by 2022. Meeting this demand and building in a much-needed reserve margin of about 10 per cent means conventional power capacity will have to reach 25,500MW by 2022, an 80 per cent growth in capacity.

Water projects are moving ahead too as MEW embarks upon a 400 million imperial-gallons-a-day (MIGD) drive to meet demand for water, which is among the highest per capita in the world.

The IWPPs at Al-Khiran and Al-Zour North 2 will add 227 MIGD. Further expansion at Al-Zour North could add another 85 MIGD in phase 3.

At the same time, the ministry is pursuing the construction of a new desalination plant at Doha, using reverse osmosis, to be delivered in two 50-MIGD stages.

 

A MEED Subscription...

Subscribe or upgrade your current MEED.com package to support your strategic planning with the MENA region’s best source of business information. Proceed to our online shop below to find out more about the features in each package.

Take advantage of our introductory offers below for new subscribers and purchase your access today! If you are an existing client, please reach out to your account manager.