Aramco restrains spending

18 January 2015

Plunging oil prices mean the oil major will hold back spending on long-term, export-oriented schemes and instead focus on projects that boost domestic gas supply and deliver job creation

After a disappointing 2013, Saudi Arabia’s hydrocarbons projects market made a decent recovery in 2014 although the value of contract awards was still way down on the huge sums signed off in 2011 and 2012.

The kingdom spent about three times more in 2014 than in 2013, with project spending across all hydrocarbons sectors hitting a total of $12.1bn, according to regional projects tracker MEED Projects. This is a major improvement on the $3.9bn spent the previous year, but still some way off the $20bn-plus years of 2011 and 2012.

Jizan plant

However, the figures do not include the $8.5bn budget for the integrated gasification combined-cycle power plant that is under construction at Jizan Economic City. There are certain packages of that scheme that many would consider to be related to oil and gas rather than power production, not least the gasification unit itself as well as the sulphur recovery unit. If these two packages were included in the oil and gas figures then spending for 2014 would be around the $17bn-$18bn mark, which would represent a far more positive scenario.

Despite this sector-based anomaly, there is no question that many international engineering consultancies and contractors working in the kingdom believe 2014 offered the last real chance of winning any significant new projects. For many, the glory days of the past five years have well and truly gone.

“The buzz is definitely not there in 2015 and it was not really there in 2014 either,” says a senior executive from a major engineering, procurement and construction (EPC) contractor. “If you look at the pipeline of potential projects coming up, most of the big ones are several years away and the low oil price is only going to make matters worse.”

Project delays

Lower oil prices have already meant Aramco has postponed the $3bn Ras Tanura refinery clean fuels rehabilitation and expansion programme. This scheme was originally going to be awarded between late 2013 and early 2014, but was retendered by Aramco after the initial bids submitted came in too high. Now it looks as though the project will not move until at least 2016.

Alongside the Jizan gasification scheme, two other major schemes accounted for more than 50 per cent of the total contract awards in 2014.

In October, Italy’s Saipem was awarded a $2bn deal by Aramco to build the main processing facilities at its onshore Khurais oil field expansion in the Eastern Province. Aramco is planning to add 300,000 barrels a day (b/d) to the field’s current capacity of 1.2 million b/d.

The Khurais expansion is part of a wider trend for the firm’s upstream oil sector, as it looks to increase capacity at newer fields while simultaneously reducing output from more mature assets.

Khurais represented Aramco’s only major upstream investment in 2014, but the state oil company is in the process of altering its strategy. The next year will see a long-term contract being signed with up to four EPC contractors to carry out work on offshore assets.

Key fact

The largest project expected to be awarded in the kingdom in 2015 is the $5bn Fadhili gas processing plant

Source: MEED

Master gas expansion

The other major award was for Aramco’s Master Gas System Expansion (MGSE) and was made to China’s Sepco in October.

The scope of work includes the EPC of two booster compressor stations, as well as all associated works including offsite and utilities. The location is between Dammam in the Eastern Province and Riyadh, and the value of the deal is $1.3bn.

The MGSE is being implemented to meet increased gas demand from the kingdom’s Central Region and Western Province. Once the scheme has been completed, it will be able to provide 9.6 billion cubic feet a day (cf/d) of gas using the booster compressor stations and pumping stations.

Gas is one sector that is not going to be affected by the low crude prices as Aramco looks to maximise output in order to feed insatiable domestic demand brought about by industrialisation and increased power generation.

The largest project expected to be awarded in 2015 is the $5bn Fadhili gas processing plant that Aramco already has out to tender with international EPC contractors. MEED reported in November that the capacity for the facility was being increased from 1 billion cf/d to 2.5 billion cf/d. This has pushed the project’s budget up from the original $3bn figure.

The Fadhili plant will process sour gas from the Khursaniyah oil field and the Hasbah non-associated gas field. Aramco has ramped up its offshore non-associated gas operations in the Gulf in recent years and is developing several fields in the region. These include the Karan, Hasbah and Arabiyah fields.

Fadhili essential

“Fadhili is essential if Aramco wants to process the really sour gas it has in some of its offshore fields,” says the senior EPC executive. “This is why it is still going ahead.”

Other likely gas projects include the second phase of the MGSE as well as some movement in the kingdom’s modest, but extremely important, tight gas scheme in the north of the kingdom.

Fadhili and the MGSE make up the majority of the kingdom’s $12bn-worth of hydrocarbons schemes at the front-end engineering and design or main contractor phases, and will be the main focus for most international EPC contractors in 2015.

Long-term strategy

With the volatility in global oil markets, it is likely 2015 will see only the most pressing schemes go ahead. Anything that is aimed at domestic job creation and industrial development will have a better chance of being given the green light by Aramco than something that is part of a long-term, export-oriented strategy.

Major oil and gas projects in Saudi Arabia
Project nameSectorBudgetStatus
Fadhili gas plantGas$5bnMain contract tender
Ras Tanura clean fuels upgradeRefining$3bnOn hold
Khurais oil field expansionUpstream$3bnExecution (extended)
Master gas system expansion: phase 2Gas$3bnPrequalification
Shoaiba bulk plantMidstream$600mOn hold
Tight gas developmentGas$200mMain contract tender
Source: MEED Projects

The years 2009 and 2010 showed that Aramco likes to operate in a counter-cyclical manner, especially when there are vast savings to be had in terms of material costs for megaprojects. If prices for other commodities such as steel and aluminium fall in line with oil prices then Aramco may decide to take advantage of these low costs and fast-track any number of schemes.

However, Aramco’s spending spree that began in 2009 was initiated after a long period of consolidation and was spurred by a real requirement to increase capabilities across several key operational areas. It would be extremely surprising if the world’s largest oil company decides to repeat this strategy so soon.

Strategy: Riyadh acknowledges new oil price era

Saudi Arabia’s oil production figures have never been the brunt of so much scrutiny, or anger, as in 2014, and this is going to continue well into 2015.

The past six months have witnessed oil prices plummet to levels not seen since the global economic crisis of 2009 and many have laid the blame firmly at Riyadh’s door. The decision taken by Saudi Arabia to maintain production of about 9.7 million barrels a day (b/d) is a major reason crude prices have fallen to below $50 a barrel as of mid-January, after they were sitting comfortably at about $110 a barrel in June 2014.

Despite the massive drop in prices, Riyadh earned $278.9bn in government revenues in 2014, 22 per cent more than its own forecast of $225bn. Oil exports account for 90 per cent of the kingdom’s export revenues and 85 per cent of government revenues.

The decision to maintain or even increase market share was not taken lightly and resulted in Saudi Arabia being accused of using oil as a weapon to ‘punish’ rivals such as Iran and Russia, as well as to halt the onslaught of unconventional oil in the US and Canada. It is possible Riyadh did consider all these factors when making its decision, but it is also probable that they are viewed as an added bonus rather than a clear strategic plan.

Despite being the world’s swing producer, there is nothing the kingdom can do about global demand, and if key economies in Asia and Europe are slowing down then it becomes a question of who can maintain market share.

It is not Saudi Arabia’s job to subsidise other producers with low profit margins by keeping prices artificially high and Riyadh has countered all accusations by stating that everyone will benefit if low oil prices become a de facto global stimulus plan.

The government’s current stance is not likely to last forever, and if prices continue to plummet (some experts are even predicting oil bottoming out at $20-$30 a barrel) then
production is almost certain to ease down to 8-9 million b/d.

The events of the past six months suggest a new pluralism in the future global oil market, with a far more diverse supply than has ever been witnessed before. Maybe Saudi Arabia’s current actions are a direct result of the kingdom being the first traditional oil producer to acknowledge this new revolution.

A MEED Subscription...

Subscribe or upgrade your current MEED.com package to support your strategic planning with the MENA region’s best source of business information. Proceed to our online shop below to find out more about the features in each package.