The Oman Electricity Transmission Company (OETC) has outlined the planned grid connection schedule for four 1GW solar independent power projects (IPPs) that will support the sultanate's renewable energy expansion through 2030.
The projects are detailed in OETC's Five-Year Annual Transmission Capability Statement (2026-30), which sets out the transmission infrastructure required to integrate new generation capacity into the national grid.
According to the report, the first of the four gigawatt-scale projects, the Adam solar IPP, is scheduled for integration in 2028.
Oman’s Nama Power & Water Procurement Company (Nama PWP) issued a request for qualification for the development of the Adam solar IPP in June.
OETC said it expects the 1GW Al-Kamil 2 solar project to be integrated in 2030 through the planned Sadaf 400kV grid station. The 1GW Dhofar solar IPP and 1GW Mahadha solar IPP are also scheduled for integration in 2030.
Before the gigawatt-scale projects are connected, several smaller utility-scale solar schemes are expected to enter service.
The first is the 500MW Ibri 3 solar project, supported by the Al-Sebkha 400kV switching station. Construction began on Ibri 3 in January.
The report says this will be followed by the Al-Kamil 1, Sinaw and Marsa solar IPPs.
The power purchase agreement for the 500MW Al-Kamil IPP was recently signed by a separate consortium comprising France's EDF Power Solutions, Oman National Engineering & Investment Company and the local OQ Alternative Energy.
Nama PWP has issued a supervisory consultancy tender for the 280MW Marsa IPP in North Al-Batinah Governorate, with a bid submission deadline of 26 July.
The transmission statement says about 70 transmission projects are expected to enter service between 2026 and 2030.
The programme is intended to increase transmission capacity, connect new renewable generation, strengthen grid reliability and support electricity demand growth across the sultanate.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF
Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions > INDUSTRY REPORT: Dubai eyes tourism sector recovery > DATA CENTRES: Big Tech falls short on data centre promise > LEADERSHIP: Aramco’s citizen developers accelerate digital change |
You might also like...
Saudi construction hits fastest growth in 2026
07 July 2026
Funds are shaping integrated mobility platforms
07 July 2026
A MEED Subscription...
Subscribe or upgrade your current MEED.com package to support your strategic planning with the MENA region’s best source of business information. Proceed to our online shop below to find out more about the features in each package.
Take advantage of our introductory offers below for new subscribers and purchase your access today! If you are an existing client, please reach out to your account manager.