10 groups submitted bids for 600MW capacity expansion
Germanys Siemens has submitted the lowest total price for the contract to expand Dubais M Station power plant by 600MW.
Siemens alternative bid, main price plus option, of AED1,442m ($392m) was lower than the AED1,463m alternative bid submitted by Chinas Sepco III. Sepco IIIs primary price of AED1,392m was, however, marginally lower than Siemens main bid of AED,1395m.
The local Ghantoot and China Power submitted the third and fourth total prices of of AED1,750m and AED1,753m respectively.
The work will involve expanding the capacity of the existing 2,030MW Jebel Ali plant by 600MW.
The contract is one of 1,900MW-worth of power generation projects for which Dubai Electricity & Water Authority (Dewa) has issued tender documents in 2014.
Bidders for M Station contract | ||
---|---|---|
Company | Main bid | Main bid plus option |
Siemens (Germany) | 1,395 | 1,442 |
Sepco III (China) | 1,392 | 1,463 |
Ghantoot (Local) | 1,702 | 1,750 |
China Power (China) | 1,677 | 1,753 |
Abeinsa (Spain) | 1,750 | 2,135 |
Duro Felguera (Spain) | 2,056 | 2,141 |
Doosan (South Korea) | 2,191 | 2,288 |
Metka/Archirodon (Greece) | 2,335 | 2,422 |
Alstom (France) | 2,429 | 2,607 |
Posco (South Korea) | 2,660 | 2,808 |
Source: MEED |
The utility has also issued tender documents in recent months for both the 100MW second phase of the Mohammed bin Rashid al-Maktoum Solar Park independent power project (IPP) and the 1,200MW Hassyan clean-coal-fired IPP.
Dewa has invited 24 prequalified firms to submit bids for the contract to develop the second phase of the solar park. The utility has set a bid submission date of 23 October.
The Netherlands KPMG has been appointed as financial adviser and the UKs Norton Rose Fulbright has been chosen as legal adviser for the planned solar project, which will use photovoltaic (PV) technology. The scheme is scheduled to be fully operational in 2017.
Dewa has invited eight groups to submit proposals by 26 January for the Hassyan IPP. In February, the authority appointed a consortium led by the UKs EY as adviser for the scheme. Dubai has set a commissioning date of 2020 for the coal plant.
You might also like...
Iraq signs deal to develop the Akkas gas field
25 April 2024
Emaar appoints beachfront project contractor
25 April 2024
Acwa Power signs $356m Barka extension
25 April 2024
AD Ports secures Angola port concession agreement
25 April 2024
A MEED Subscription...
Subscribe or upgrade your current MEED.com package to support your strategic planning with the MENA region’s best source of business information. Proceed to our online shop below to find out more about the features in each package.