The scheme is trying to keep up with rising electricity demand
Value: $4.6bn
Client
Kahramaa
Ahmed al-Nasser
Tel: (+974) 4 484 5111
Consultant (phase 11)
Energoprojekt
Goran Savic, project manager
Tel: (+974) 4 447 8571
Qatar has the highest electricity reserve margin in the region and one of the best transmission networks in the Middle East. This is the result of massive investment in transmission projects stretching back. Qatar General Electricity & Water Corporation (Kahramaa) is estimated to have spent more than $15bn on power projects during 2000-12.
Much of this has been spent on the Qatar Transmission Project, an ongoing programme of upgrades to the electricity transmission infrastructure of the country, which is now in its eleventh phase. Electricity supply is being boosted to meet the needs of a rapidly expanding population and to satisfy the rising demand that comes from Qatar’s many planned projects, as the country gears up to host football’s Fifa World Cup in 2022.
The number of high-voltage substations in Qatar’s electricity network should rise 50 per cent by 2016
At the end of March 2012, Kahramaa awarded 10 electricity packages covering 34 substations, including 24 new stations, double-circuit, high-voltage underground cables nearly 400 kilometres long, and 100km of overhead lines. This work is scheduled to be completed in 2015. The number of high-voltage substations in Qatar’s electricity network should rise 50 per cent by 2016, compared with 2012 levels.
Phase 11 of the project, launched last year, should be worth about $4.6bn and primarily focuses on substation and cabling contracts. It will be executed in two phases. Overall, it includes the installation of about 70 substations.
In 2008, Qatar’s first 400kV power line was installed by France’s Nexans in consortium with Italy’s Prysmian, under the seventh phase of the transmission project.
The 16km line was divided in 33 sections of about 480m in length and comprised three cable circuits. The 400kV power line was installed to replace overhead pylons.
Key dates
December 2012
Phase 8 complete
February 2013
Phase 9 due for completion
July 2013
Main contract tender issue for phase 11 stages 1 and 2
June 2015
Phase 10 due for completion
August 2015
Phase 11 stage 1 due for completion
April 2016
Phase 11 stage 2 due for completion
Source: MEED Projects
You might also like...
Oman receives Madha industrial city tender prices
19 April 2024
Neom seeks to raise funds in $1.3bn sukuk sale
19 April 2024
Saudi firm advances Neutral Zone real estate plans
19 April 2024
Algeria signs oil deal with Swedish company
19 April 2024
A MEED Subscription...
Subscribe or upgrade your current MEED.com package to support your strategic planning with the MENA region’s best source of business information. Proceed to our online shop below to find out more about the features in each package.